BRIDGWATER – The UK’s flagship electric vehicle battery project is in disarray after its second major construction contractor walked away in five months. TSL, the firm tasked with building the £5.2bn Agratas gigafactory in Somerset, has decided to exit the project after failing to reach an agreement on costs and timelines, according to three sources familiar with the dispute.
The departure leaves the site without a lead builder, raising sharp questions about whether the plant will begin producing batteries for Jaguar Land Rover in January 2028 as planned. This is the second time in half a year that the project has lost its primary construction partner, following the abrupt dismissal of Sir Robert McAlpine in June. Sources indicate that TSL is expected to fully vacate the site within two to three months, leaving Agratas to scramble for a replacement.
Cost Clashes Derail Key Industrial Hub
The friction between Agratas and TSL mirrors the issues that led to the previous contractor’s departure. Disagreements over the scale and pace of the build have created a bottleneck at what is considered vital for the long-term health of the British car industry. The UK government has pledged £380m in financial support for the facility, viewing it as essential to reducing dependence on battery supplies from China, South Korea, and Japan. However, not all of this subsidy has been disbursed, and further delays could complicate the funding stream.
Morale within the company has also taken a hit. Agratas recently decided to relocate some engineers from its Coventry office to Somerset, a move that has prompted some senior staff to consider leaving rather than uprooting their families. This exodus of talent adds to the operational headwinds facing the project as it prepares for its launch phase.
“We are on track to meet our customer requirements. The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility’s launch phase,” said an Agratas spokesperson.
Despite the turmoil, physical progress continues. The building shell is largely complete, and National Grid has begun work on the high-capacity electricity substation required to power the battery manufacturing lines. Agratas managers traveled to India this week to coordinate with counterparts at the sister plant in Sanand, seeking to streamline operations and share best practices.
Shadows of Britishvolt Loom Over Future
Observers note that the situation echoes the collapse of Britishvolt, another UK battery project that failed to secure firm orders and is now being converted into an AI data center. While Agratas has secured a long-term supply deal with JLR, the lack of a stable construction partner remains a critical risk. Analysts suggest that NG Bailey, the current mechanical and electrical contractor, could be a candidate to take over the entire build, but no formal announcement has been made.
JLR has secured batteries from other suppliers for its immediate model launches, meaning near-term sales of electric Land Rovers and Jaguars will not be impacted. However, those vehicles will not feature British-made cells, potentially complicating the company’s strategy to navigate EU tariffs and meet domestic content rules. The next few weeks are critical. As Agratas seeks a new lead contractor, the market will be watching closely to see if the January 2028 production target survives the latest setback or if the timeline slips once more.